Stairs.  Entry group.  Materials.  Doors.  Locks.  Design

Stairs. Entry group. Materials. Doors. Locks. Design

» Connection of the channel to the thermal chamber. Thermal cameras. Thermal cameras and their applications

Connection of the channel to the thermal chamber. Thermal cameras. Thermal cameras and their applications

1. On heating networks in polyurethane foam insulation from the top of the fixed support shield to the ground must be less than ≥ 0.5m .

2. When changing an existing channel installation in insulation of min. cotton wool for ductless, a fixed support must be installed on a pipeline in polyurethane foam insulation , and the existing- dismantle.

3. Air vent on a ductless pipeline set between 0,2 < В < 0,5 м. от земли .

4. If the ventilator operating on the main route is not implemented within the established depth limits, it can be placed on the subscriber branch before the valve.

5. Angles on heat pipes in polyurethane foam should be as standard as possible: 30°, 45°, 60°, 90°.

6. Deepening of PPU pipelines for pipelines with a diameter of more than 325- up to Zm.

7. Laying pipelines in polyurethane foam insulation under the road :

- In the case (sleeve):

if possible, install supply (12.0 linear meters long) and receiving pits outside the roadway;

the length of the case should not exceed 9.0 linear meters.

When justified, as an exception, 1 joint in the sleeve can be implemented.

- In through and semi-through channels, on sliding supports with mandatory provision of gravity water removal from the channel.

- In unloading structures with sanding (provided that there is a possible, in the future, unhindered opening of the road surface, if from the bottom of the road surface to the top of the pipe there is more<0,6 м.)

8. When designing, take the length of pipelines in polyurethane foam insulation equal to = 11.5 m (for all diameters)

9. When laying pipes in polyurethane foam insulation in passageways and semi-bore channels, channel dimensions must provide the ability to work with joints (couplings). The distance from the pipeline insulation to the channel wall should be taken at least-0.5 m. As an exception, in cramped conditions for diameters up to 150 mm, the distance can be reduced to 300 mm.

10. When soils with a design resistance of less than 1.5 kg/cm 2 under pipelines in polyurethane foam insulation should be provide an artificial foundation .

11. On pipelines in polyurethane foam insulation with a diameter of up to 159 mm inclusive, the permissible oblique joint with a sealed coupling is 5°. For diameters of 219 mm and above, an oblique joint of up to 2.5° is allowed. At large angles, bends should be provided.

12. Joints on pipelines V PPU isolation place behind outside crossed communications And aisles through walls buildings And cameras .

13. It is recommended to install starting compensators on pipelines in polyurethane foam insulation with DN 400mm and more, up to- DN 400 mm use natural compensation.

14. Insert branches in the coverage area of ​​the starting compensator no closer than 10 m from the compensator, with its reconfiguration.

16. Pipeline kinks are not allowed in the area of ​​​​operation of the starting expansion joints.

17. A fixed support (hereinafter n.o.) is not placed in the wall of the building ( min 1 m from the wall of the building.) ( BUT. can be installed inside the ITP).

18. Shut-off valves should be installed at the boundary of the pipelines’ balance sheet.

19. On branches up to the shut-off valves, the thickness of the pipeline wall must be no less than the wall thickness of the main pipeline.

20. The water outlet must have a minimum slope of 0.003

-Water outlet from the descents - preferably gravity drainage into an existing or planned drain.

- Water release is allowed if justified:

a) into a separate water intake well with subsequent pumping into an existing or projected drain.

b) water absorption well.

c) construction of a drainage pumping station (DPS).

- Water outlet from building structures:

a) gravity flow into an existing or designed drain.

b) construction of a drainage pumping station (DPS).

21. In sections of pipelines DN 800 mm or more, with bellows expansion joints, passage channels should be provided, and fixed supports should be designed for the maximum possible loads.

Requirements for the design of thermal chambers

1. In the thermal chamber, the shut-off valves should be located as close as possible to the insertion, and unobstructed access to it should be provided for maintenance and repair.

3. If the distance from the floor to the shut-off valves in the chamber is more than 1.5 m, a service platform is installed.

4. The thermal chamber must have at least two inspection hatches, located diagonally.

5. If water is removed from the drains and the heat chamber is discharged from the pit into one well, a valve should be installed in the pit.

Air and drain valves, thermometers and pressure gauges on underground heating networks are made by chambers, the dimensions of which in plan depend on the diameter of the heat pipe and the possibility of unhindered maintenance of the equipment installed in the chamber. The height of the chamber is made at least 2 m. The ceilings of the chambers are mounted from prefabricated elements of reinforced concrete slabs, in which holes are provided for cast iron hatches - at least two per chamber. The walls of the cells are of two types: made of prefabricated reinforced concrete slabs and large blocks. Monolithic walls are rarely made.

Installation of a reinforced concrete chamber from prefabricated structures consists of the following: preparation of the base; laying the base slab; installation of wall blocks and their temporary fastening (if necessary); laying floor slabs; caulking or sealing seams and preparing the outer surface for waterproofing; installation of hatches; installation of manhole covers.

In some cases, caused by necessity, with appropriate justification, the construction of chambers from monolithic reinforced concrete is allowed. The main disadvantages of using monolithic reinforced concrete are the large number of work processes performed manually and long work periods due to the need for curing the concrete during hardening.

Assembly of a reinforced concrete chamber

a, b - laying base slabs:
c, d— installation of G-framed blocks; d - laying floor slabs

Increasing the reliability and durability of heating networks under construction is greatly facilitated by the organization and implementation of technical supervision, especially over the construction of prefabricated reinforced concrete structures, the installation of their waterproofing, and the sealing of butt seams. For example, the discrepancy between the sizes of holes in the walls of chambers for the passage of pipes and the design values ​​(cross-sectional area of ​​the channels) requires additional work to carefully seal and seal the resulting gaps and cracks (at the junction of the channels with the walls of the chambers). As a result, conditions are created in these places for water to penetrate into the chambers and channels. For this reason, sections of heat pipes near the walls of the chambers are most often subject to severe damage by corrosion.

Reinforced concrete thermal chambers are high-strength special-purpose products that are used when laying underground communications: water supply systems, sewerage systems and gas networks. Thermal chambers, or as they are also called heating chambers, are used to accommodate heat pipeline units, as well as equipment that requires constant maintenance during operation and, if necessary, repair. In addition, cameras are used to interface pipes of different sizes and intersect them.


The following equipment is installed in thermal chambers: valves, stuffing box expansion joints, drainage and air devices, instrumentation and other equipment. Branches to consumers and fixed supports are also installed in the chambers.


The main areas in which thermal cameras are used are civil, housing and engineering construction. The high strength of these makes it possible to protect underground communications from adverse environmental factors, vibrations from vehicles passing over the pipeline, soil pressure, as well as from unauthorized or accidental entry of humans and animals. Heating network chambers have increased strength and waterproofing.


Thermal chambers are immersed to a maximum design depth of 4 m. The depth of the top of the chamber floor is assumed to be at least 0.3 m. To drain random water along the bottom of the chambers, a slope with a cement-sand screed is created, directed towards the pits. In damp soils, accompanying drainage is laid along the heat pipeline line so that the groundwater level does not rise above 1 m from the bottom of the chambers.


Depending on the design features of the thermal chambers, they are divided into two types:

  • chambers made of prefabricated blocks;
  • chambers made of prefabricated slabs and panels.

Reinforced concrete thermal chambers made of prefabricated blocks consist of the following elements:

  • upper block of the VBK chamber. The upper part of the chamber, which is an inverted box. The top surface of the block may have one or more round holes for passage into the chamber, on the side surfaces - one or more round or rectangular holes for passage of pipes;
  • middle block of the SBK chamber. A through square ring, on the side surfaces of which there may be holes or openings for passing pipes;
  • lower block of the NSC chamber. The box with an open top is the bottom of the heating chamber.
  • middle panels of the SPK chamber. Rectangular slabs, allowing the construction of chambers of various heights, can be used instead of medium blocks;
  • upper plates of the military-industrial complex chamber. They are used in conjunction with the middle panels of the chambers and act as floor slabs for the chambers. The slabs have holes for access to communications and equipment.

Thermal chambers made of prefabricated slabs and panels include the following elements:

  • chamber floor slabs P. Perform the function of a chamber cover. They have round holes for access to communications and equipment;
  • wall panels of PS, PSU chambers. Rectangular slabs for designing chambers of various widths and heights;
  • foundation blocks of chambers F, FU. Serves as the bottom of the chamber. They have grooves for installing wall slabs;
  • chamber beams B. They are installed on wall slabs and serve as a support for the chamber floor slabs.

In dry soil, the lower blocks of the chambers are installed on a sand leveling layer 10 cm thick, and when installed in wet soil - on a concrete preparation 10 cm thick. The middle and upper blocks are installed on a cement mortar of 1/3 composition. The blocks and panels are secured to each other using overlay parts welded to the embedded parts of the blocks.


Thermal chambers are manufactured in accordance with series 3.903 KL-13 “Heat supply. Prefabricated reinforced concrete chambers on heating networks."


The material from which the thermal chambers are made is hydraulic concrete. The compressive strength class of concrete is B22.5. The tempering strength of concrete is taken to be no lower than 70% of the design strength. The concrete class for frost resistance is assigned to F150, and for water resistance – W4.


Reinforced concrete thermal chambers are reinforced with welded mesh and frames made of hot-rolled steel rods of the following classes: A-I and A-III - for chambers made of prefabricated blocks; A-I, A-II and A-III - for chambers made of prefabricated slabs and panels. For ease of installation of prefabricated products, lifting loops are made of smooth reinforcing steel of class A-I.


Reinforced concrete thermal chambers are marked with an alphanumeric designation. The brand of thermal cameras contains numbers characterizing the overall dimensions - length, width and height in meters. Prefabricated chamber blocks contain letters indicating the position of the blocks in the chamber (NBK - lower chamber block, SBK - middle chamber block, VBK - upper chamber block), and numbers indicating the main dimensions of the chamber where the block is installed - length, width and height in meters. The presence of hatches or holes in the blocks is indicated by the size of these holes in the denominator.


Chambers are installed in places where heat pipeline equipment is installed: valves, stuffing box expansion joints, drain and air valves, dead supports, etc.

The construction part of the chambers is often made of brick, as well as monolithic concrete or reinforced concrete. boron reinforced concrete is mainly used for flooring.

In the construction of heating networks in Moscow, prefabricated reinforced concrete chambers with a round and rectangular outline have been used.

Chambers made of round reinforced concrete rings with an internal diameter of 1.5 and 2 m, used on heat pipeline routes with a diameter of up to 150 mm, have become widespread.

The design of the round chamber is made up of three types of blocks: rings without holes, rings with holes for passing pipes and floor slabs.

1 - floor slab;

2 - block without holes;

3 - block with holes;

4 - compacted crushed stone;

5 - opening for passing pipes;

6 - cement mortar;

7 - pit;

8 - preparation from concrete M-75

The walls of the chamber are assembled from three ring blocks, superimposed on each other. To pass pipes, one of the ring blocks has openings. This block is usually installed in the top or middle row, which corresponds to the normal depth of heat pipes from the ground surface (0.8-1.5 m).

The lower ring block is installed on a preparation made of M-75 concrete with a thickness of 150 mm. A crushed stone layer 50 mm thick is laid under the concrete preparation.

A round floor slab is laid on top of the upper annular block, which has an edge and two holes for installing inspection hatches. Manholes are usually made of brickwork and covered with standard cast iron hatches. The outer surfaces of the chamber are covered with hot bitumen 2 times.

In the construction of heating networks, the design of chambers made of prefabricated reinforced concrete sections of rectangular shape was used.

1 - wall block without holes;

2 - wall block with holes;

3 - bottom block;

4 - overlap block

Typical camera designs are designed for internal dimensions of 1.5x1.5; 1.5x2 and 2x2 m.

The rectangular outline of the chambers has some advantage over the round one in terms of more convenient maintenance of the heat pipeline equipment located in the chamber. This design consists of rectangular closed links superimposed on one another. The rectangular links from which the walls of the chambers are assembled are made of two types: without holes and with holes for passing pipes.

Since 1970, a new prefabricated design of rectangular chambers with walls made of vertical blocks was developed and implemented. Prefabricated chambers of this design are designed for five plan sizes (1.5 x 1.5; 1.5 x 2; 2 x 2; 2 x 2.5 and 2.5 x 2.5 m) and are assembled from wall blocks and floor and pit floor blocks.

The wall block is an L-shaped slab, the short side of which serves as its base, and the long side forms the wall of the chamber. Reinforcement in the form of loops is released from the short side of the block.

The blocks are manufactured in two types: solid and with a rectangular hole for passing pipes.

The corner wall block has the shape of a corner in cross section.

The bottom block is rectangular in shape, with reinforcing loops on four sides.

The floor slab has a rectangular shape with holes for hatches.

The minimum depth of the chambers is taken to be 0.3 m, counting from the surface of the earth or road surface to the top of the ceiling . The location of the holes in the wall blocks in height is based on the most common depths for laying heat pipes in design practice, of the order of 1-1.5 m. With deeper laying of heat pipes, the height of the backfill above the top of the floor increases by deepening the bottom of the chamber.


a - size 150×150 cm;

b - size 250×250 cm

Installation of cameras from vertical blocks is carried out in the following sequence. In an open pit, preparation is made from M-75 concrete. For preparation, bottom blocks and corner and middle wall blocks are installed over a layer of cement mortar, which ensures their correct position. After passing the reinforcement and tying it with the loop reinforcement of the blocks, the gap between the wall blocks and the bottom block is filled with M-200 concrete. The seams between the wall blocks are sealed with M-50 grade cement mortar by pouring it into the grooves from above.

Beams and floor slabs in cement mortar are laid on top of the wall blocks. The seams between the slabs are also sealed with cement mortar.

The outer surfaces of the walls and ceilings are covered with a layer of hot bitumen 2 times. When the chambers are located in conditions of a high groundwater level, it is necessary to install an adhesive waterproofing system consisting of two layers of waterproofing material. In some cases, external plaster with waterproof cement mortar can be used.

The advantages of the described design of prefabricated rectangular chambers are the simplicity of manufacturing the blocks and the ease of their transportation and installation.

The main advantage of the design of prefabricated chambers with walls made of vertical blocks is the uniformity of the wall blocks of the chambers and semi-through channels, differing only in size and height. This greatly simplifies the organization of the production of all prefabricated parts of heating systems at the factory. Thanks to the simple configuration of the blocks, their production does not cause any difficulties for any construction organization at any time of the year. Installation of the camera does not require heavy equipment and devices for temporary fastening of blocks during assembly. The sealing of block joints in winter conditions can be done from inside the chamber.

The great advantage of the structure is its stability, achieved by monolithic wall blocks with bottom blocks.

The use of prefabricated chambers of round and rectangular shapes makes it possible to completely industrialize the construction of heating networks. Large chambers can be constructed from prefabricated blocks of the types described above. For the construction of large chambers, rectangular concrete blocks are most widely used. The blocks are made of M-100 concrete and have length dimensions of 1; 1.5 and 2 m and a section of 0.5X0.6 m. The walls of chambers of all sizes in plan and height are made from these concrete blocks. When the height of the chambers is more than 2 m, reinforcing mesh is placed in the horizontal seams between the blocks. If the dimensions of the chamber in plan require the insertion of blocks of dimensions smaller than 1 m, then the gaps between the standard blocks are filled with monolithic concrete.

Large chambers for large-diameter heat pipes are made of monolithic reinforced concrete.

The Mosinzhproekt Institute has developed unified chambers made of prefabricated reinforced concrete vibro-rolled panels for underground communications. The cameras can be used for heating pipelines with a diameter of up to 600 mm, as well as water pipelines with a diameter of up to 900 mm and gas pipelines with a diameter of up to 600 mm.

These chambers house the fittings and equipment of the most typical units of heating networks.

The chambers are constructed from separate volumetric elements - cabins, assembled at the factory from rectangular reinforced concrete slabs. Volumetric cabins are assembled from bottom slabs, floor slabs, walls and longitudinal frames. The slabs are produced by the method of continuous vibratory rolling on mills of the engineering system. N. Ya. Kozlova. The slabs are connected to each other using gussets welded to the embedded parts.

The design of the cabin allows the floor slab to be removed during installation work or equipment replacement without compromising its stability. By combining several booths, different types of chambers can be obtained to accommodate heat pipe equipment. Fixed supports made of monolithic reinforced concrete are arranged between two adjacent cabins. Fixed shield supports can be located outside the chamber, which is usually done when constructing chambers for branches of heat pipelines. The figure shows a diagram of a chamber for placing stuffing box compensators and branches, composed of two cabins.

Structures along the route of heat pipelines for the installation of equipment that requires post, inspection and maintenance during operation. In the chambers of heating networks there are valves, stuffing box compensators, drainage and air devices, control and measurement. instruments and other equipment. In addition, they usually install branches to consumers and fixed supports. Transitions of pipes of the same diameter to pipes of another diameter must also be within the limits of K.t.s. All K.t.s. installed. along the heating network route, are assigned exhiuatats. numbers, with which they are indicated on plans, diagrams and piezometric. graphs. The equipment placed in the chambers must be accessible for maintenance, which is achieved by ensuring sufficient distances between the equipment and the walls of the heating network chambers. Height K.t.s. choose at least 1.8-2 m. Their internal. Dimensions depend on the number and diameter of the pipes being laid, the dimensions of the installed equipment and imaginary ones. distances between buildings, structures and equipment. K.t.s. They are built from brick, monolithic concrete and reinforced concrete. Openings are left in the end walls to allow heat pipes to pass through. Floors in K.t.s. made from prefabricated reinforced concrete. slabs or monolithic. For water drainage, the bottom is made with a slope of at least 0.02 towards the receiver, which is for the convenience of pumping water from the boiler. located under one of the drains. The ceiling can be monolithic or made of prefabricated reinforced concrete. slabs, laid on reinforced concrete. or metallic beams. To install hatches, slabs with holes are laid in the corners of the ceiling. In accordance with the safety rules during operation, the number of hatches for K.t.s. at least two are provided for internal chamber area up to 6 m and at least four for an area of ​​more than 6 m2. To descend the service personnel, brackets are installed under the hatch, arranged in a checkerboard pattern with a height increment of no more than 400 mm, or ladders. If the dimensions of the equipment exceed the dimensions of the entrance hatches, installation openings are provided, the width of which is equal to the largest size of the fittings, equipment or pipe diameter plus 0.1 m (but not less than 0.7 m). Industrial chambers for heating networks made of prefabricated reinforced concrete are widespread, the installation of which takes less time and reduces labor costs.

Professional boiler room installation

    installation of heating radiators;

    assembly and installation of a boiler room;

    pressure testing of the system;

    description of the Work Completion Certificate;

    commissioning works;

    removing air from the heating system;

Prefabricated structures of rectangular c.t.s. are also used. with vertical walls. blocks, of which there are two types: solid and with rectangular holes for the passage of heat pipes. When constructing heating networks of small diameter K.t.s. can be made from round reinforced concrete. rings Round floor slabs have two holes for inspection hatches.

On main lines and heating networks with a diameter of 500 mm or more, sectional valves with an electric drive are installed, as a rule, in heating systems, above which above-ground structures in the form of pavilions are built. The design of repair work in the pavilions includes lifting equipment. For waterproofing. protection of the outer surfaces of the bottom and walls of the K.t.s. in the presence of a high groundwater level, despite the existing associated drainage, cover

glued waterproofing made of bitumen

rolled materials in several layers,

what is determined by the project. In conditions

increase waterproof requirements

bridges, except for external wrapping

additional waterproofing is used.

plaster cement-sand waterproofing internal. surfaces applied during large volumes of work using the shotcrete method.

All types of home heating :

  • wood burning

    solid fuel

    autonomous

  • diesel

    liquid fuel

    gravitational

    independent

  • HEATING NETWORK CHAMBERS

    AIR HEATING CHANNEL, heated air duct

    SEWER NETWORK

    SEWER COLLECTOR

    DROP TRAINER, separator

    BOILER FRAME

    CATALYTIC REACTOR

    APARTMENT HEATING

    CERAMIC EMBEDIER ATTACHMENT

    COAGULATION

    COAGULANTS, coagulating agents

    COAGULATION

    CONTACT COAGULATION

    HEATING SYSTEM MANIFOLD

    SOLAR ENERGY COLLECTOR

    MINE WELL

    WATER HEATER

    COMBINED CLIMATE CONDITIONING SYSTEM

    COMBINED HEATING

    COMPACT SUPPLY JET

    HEAT PIPES COMPENSATOR

    COMPENSATORY NICHES

    SEDIMENT COMPOSTING

    COMPRESSOR

    CONVEYOR

    CONVECTIVE AIR JET

    CONVECTIVE HEATING

    CONVECTIVE HEAT TRANSFER

    CONVECTORS

    CONGRUENT MELTING

    CONDENSATE

    CONDENSATE PUMP

    CONDENSATE PIPEL

    CAPACITOR

    CONDENSER IN A HEAT PUMP HEATING SYSTEM

    AIR CONDITIONER

    AIR CONDITIONING

    CONTROL AND MEASURING INSTRUMENTS

    SOLAR RADIATION CONCENTRATOR

    CONCENTRATION LIMITS OF GAS IGNITION

    CORROSIVE INHIBITOR (moderator)

    CORROSIVE PASSIVATOR

    CORROSION OF METALS

    SELECTIVE CORROSION OF METALS

    INTERCRYSTALLITE CORROSION OF METALS

    TRANSCRYSTALLITE CORROSION OF METALS

    CHEMICAL CORROSION OF METALS

    CORROSION OF METALS ELECTROCHEMICAL

    CORROSION-PITTING

    HRSG

    BOILER ROOM

    BOILER INSTALLATION

    BOILER UNIT, boiler unit

    BRIDGE CRANE

    WASH TAP

    WINCH manual

    RADIANT HEATING

    RADIANT HEAT TRANSFER

    HEATING SYSTEM MAIN

    OIL FACTORY

    MATHEMATICAL MODEL OF THERMAL AND AIR MODES OF A BUILDING

    MILL

    DIAPHRAGM DRIVE OF THE REGULATORY ORGAN

    LOCAL EXHAUST VENTILATION

    LOCAL SUPPLY VENTILATION, air showering

    LOCAL DUST COLLECTION UNIT

    LOCAL HEATING

    LOCAL AIR HEATING

    LOCAL PANEL-RADIANT HEATING

    LOCAL SUCTION

    METHANTANK

    FINITE DIFFERENCE METHOD in heat transfer

    METHODS OF CLIMATE CONTROL IN BUILDINGS

    MOISTURE TRANSFER MECHANISMS

    MICROFILTER

    MULTI-ZONE AIR CONDITIONING SYSTEM

    KITCHEN SINK

    WET DUST COLLECTORS

    INSTALLATION OF VENTILATION SYSTEMS

    WASTE INcinerator

    RELIABILITY OF GAS DISTRIBUTION SYSTEMS

    RELIABILITY OF HEATING SYSTEMS

    GUIDING APPARATUS

    PUMP BOOSTER UNIT

    PUMPING STATION

    INITIAL CONDITION

    NON-FREEZING MOISTURE IN MATERIALS

    FIXED SUPPORTS

    IMPASSABLE CHANNELS OF HEATING NETWORKS

    OIL TRAP

    GAS PIPELINES ON BOILERS AND FURNACES

    BOILER BLOWING

    BOILER BLOWERS

    DEWATERING OF NATURAL WATER SEDIMENTS

    DEWATERING OF SEWAGE SLUDGE

    DISINFECTION OF WATER WITH OZONE

    DISINFECTION OF WATER WITH UV RAYS

    WATER DISINFECTION WITH CHLORINE, disinfection

    DISINFECTION OF SEWAGE SLUDGE

    DISINFECTION OF NATURAL AND WASTEWATER

    DESILIFICATION OF WATER

    SECURITY OF SETTLEMENT CONDITIONS

    DESALINATION OF WATER

    DESALINATION OF WATER BY REVERSE OSMOSIS

    BOILER LINING

    GAS PIPELINE EQUIPMENT

    EQUIPMENT FOR ION EXCHANGE UNITS

    NATURAL GAS PROCESSING

    REINJECTION OF GEOTHERMAL WATER

    CONTROL OBJECTS WITH DISTRIBUTED AND CONCENTRATED PARAMETERS

    FENCE WITH TRANSPARENT THERMAL INSULATION

    SINGLE-PIPE WATER HEATING SYSTEM

    OZONATOR

    OKSITENK

    DESALINATION

    DESALINATION AND DESALINATION OF WATER BY DISTILLATION

    MUNICIPAL AND INDUSTRIAL SEWAGE SLUDIMENTS

    SEDIMENTS OF NATURAL WATER

    WATER CLEANER

    CONTACT CLEANER

    AIR DRYING

    SORPTION AIR DRYING

    STEAM PIPEL DRYING

    DISCHARGE OF COMBUSTION PRODUCTS FROM GAS APPLIANCES

    SEPARATOR

    OPEN HEATING SYSTEM

    RELATIVE HUMIDITY

    HEATING PANEL

    HEATING OVEN

    HEATING AND VENTILATION UNIT

    HEATING GAS OVENS

    HEATING UNIT

    BOILER

    HEATING APPLIANCE

    HEATING

    AIR SUCTION LATERAL

    RING AIR SUCTION

    WATER SETTING

    SETTLEMENT TANK

    SETTLEMENT RADIAL

    SETTING TANK WITH ROTATING DEVICE FOR WATER COLLECTION DISTRIBUTIONS

    THIN-LAYER SETTENTOR

    REJECTION

    COOLING POND, cooling pond

    AIR COOLING

    AIR COOLING DRY

    ABSORPTION AIR PURIFICATION

    CATALYTIC GAS AND AIR PURIFICATION

    PURIFYING GASES AND AIR BY CONDENSATION METHODS

    DEEP WASTEWATER TREATMENT OF SMALL SETTLEMENTS

    CLEANING AND DESALTING OF WASTEWATER BY ION EXCHANGE

    PURIFICATION OF GROUNDWATER FROM NITROGEN COMPOUNDS

    NATURAL WATER PURIFICATION AND WATER TREATMENT

    TREATMENT OF INDUSTRIAL WASTEWATER BY OZONATION

    TREATMENT OF INDUSTRIAL WASTEWATER WITH HYDROGEN PEROXIDE

    CLEANING OF DRAINS

    WASTEWATER TREATMENT IN AREAS WITH HARSH CLIMATES

    WASTEWATER TREATMENT OF GALVANIC PRODUCTIONS

    WASTEWATER TREATMENT OF INDIVIDUAL HOUSES

    WASTEWATER TREATMENT WITH OXYGEN

    WASTEWATER TREATMENT OF SMALL SETTLEMENTS

    WASTEWATER TREATMENT OF FACILITIES WITH SHORT-TERM Occupancy

    WASTEWATER TREATMENT FROM NITROGEN COMPOUNDS

    WASTEWATER TREATMENT WITH ACTIVATED SLUDGE

    INFRARED PANEL

    UNIFORM AIR SUCTION PANEL

    PANEL-RADIANT HEATING

    WATER STEAM

    SECONDARY BOILING STEAM

    OUTDOOR CLIMATE PARAMETERS

    STEAM HEATING SYSTEM

    STEAM-WATER MIXTURE

    STEAM-WATER HEATER

    STEAM HEATING

    STEAM BOILER

    STEAM PUMP

    VAPOR INSULATION

    SUPERCOOLER

    STEAM PIPEL

    VAPTOR PERMEABILITY

    PASSIVE SOLAR HEATING SYSTEM

    AIR DISCHARGE PIPE

    PELTIER EFFECT

    FOAM DUSTING EQUIPMENT

    V-BELT TRANSMISSION

    AIR OVERFLOW

    SAND TRAP

    STOVE HEATING

    Our services:

    1. Boiler room at home

      SOLAR RADIATION CONCENTRATOR - a device that focuses solar radiation onto an emitter receiver,......

    2. Boiler room at home

      DESIGN PRESTIGE LLC qualifiedly and fully carries out the complex construction of Heating networks (heating mains), including Build......

    3. Boiler room at home

      A special focus should be on the development of design documentation for laying external heating networks, design......

    4. Boiler room at home

      COMPENSATORY NICHES - structures on the route of underground heat pipelines, intended for accommodation house......

    5. Boiler room at home

      COMPRESSOR - a machine for increasing the pressure of a gaseous medium, air or steam.......

    6. Boiler room at home

      WATER HEATER - a sanitary appliance installed in bathrooms or shower rooms......

    7. Boiler room at home