» Maps of operational quality control of construction and installation works. Schemes for operational quality control of construction, repair and installation works. Testing and flushing of heating network pipelines

Maps of operational quality control of construction and installation works. Schemes for operational quality control of construction, repair and installation works. Testing and flushing of heating network pipelines

Input and operational control construction quality installation work. Part I, issue 2. Installation of prefabricated reinforced concrete structures residential buildings, installation of light enclosing structures. Trust "Orgtekhstroy-11" 2001
Schemes for incoming and operational quality control of construction and installation works are drawn up in accordance with the requirements of SNiP 3.01.01-85* “Organization construction production».
Schemes of incoming and operational control are intended for line engineering and technical workers, foremen and workers, employees of the quality control department of construction and installation work, workers of laboratory, geodetic and welding services who carry out self-control, incoming, operational and acceptance quality control of construction and installation work.
Schemes can be used:
- employees of services for the preparation of construction production as standard ones for their inclusion in projects for construction and installation works or the development on their basis of schemes that reflect the specifics of specific projects of buildings and structures;
- by employees of personnel training services as a teaching aid in the preparation, retraining and advanced training of workers and engineers;
- teaching staff of higher and secondary technical educational institutions in the training of engineering and technical workers construction profile;
- heads of divisions, main functional departments and services, as well as management construction organizations when testing the knowledge of projects and regulatory requirements for the quality of construction and installation work among line personnel, as well as when carrying out inspection control of the quality of construction and installation work;
- employees of design supervision of design organizations;
- employees of the customer’s technical supervision who accept the work performed, employees of architectural and construction supervision services, federal and regional centers for licensing construction activities and other organizations supervising construction.


Schemes for incoming and operational quality control of construction and installation works are drawn up based on the requirements of building codes and regulations, state standards, technical specifications, standard project documentation and contain:
- basic requirements for the quality of materials, structures and parts used;
- list of technological operations subject to control during construction and installation work;
- a list of technical requirements that must be observed when performing construction and installation work;
- diagrams of the main assembly units;
- basic quality requirements for acceptance of completed stages and types of work.
Building construction, products, materials and engineering equipment arriving at the construction site must undergo entrance control. Work producers (craftsmen) are obliged to check, through external inspection and taking the necessary measurements, the conformity of the quality of incoming structures, products, materials and engineering equipment requirements of working drawings, state standards, technical specifications.
When performing incoming inspection at picking bases, the foreman (foreman) must be presented with documents (passports, certificates, acts, etc.) confirming the quality of the supplied materials and products. If there are any doubts about the quality of the supplied materials, the foreman (master) is obliged to request a control check of the received product materials.
Incoming control must prevent the launch into production of materials, structures and products that do not meet the requirements of design and regulatory technical documentation. On construction site incoming inspection must be carried out by a foreman or foreman with the involvement of necessary cases laboratory and other services.
Operational control should be carried out during construction and installation work and ensure timely identification of defects and the causes of their occurrence, as well as timely adoption of measures to eliminate and prevent them.
When implementing operational control, the following must be checked:
- compliance with the work production technology specified in work projects and technological maps;
- compliance of the quality of work performed with the requirements of the project and regulatory and technical documentation.
Operational control must be carried out by the work foreman (foreman), engineer (laboratory assistant) of the construction laboratory, surveyor, welding service worker or welding laboratory worker. The participation of a particular service in the implementation of operational control must be regulated by a technological map for a specific technological process.
Acceptance control should be carried out upon completion of stages or individual types of work, as well as critical structures. Acceptance is formalized by acts of inspection of hidden work, acts of acceptance of individual stages or types of work, as well as critical structures.
Acceptance must be carried out by a foreman, employees of the quality control department for construction and installation work, with the involvement, if necessary, of workers from laboratory, geodetic or welding services, and representatives of the customer’s technical supervision.
When carrying out production control, you should use measuring instrument and instruments that have passed metrological verification within the established time limits.
Links to normative literature are given as of December 25, 2000. Data on new normative documentation and changes to the current one are given in the information indexes of Gosstandart and Gosstroy of Russia.

Explanatory note.
Installation of reinforced concrete structures of residential buildings.
Off-site and on-site preparatory work.
Construction of a geodetic alignment basis for construction.
Construction of ground rail crane tracks.
- are common technical requirements.
- geodetic work during the construction of ground rail crane tracks.
- requirements for operation.
Incoming quality control of prefabricated concrete and reinforced concrete products and designs.
- GOST 13015.0-83* Prefabricated concrete and reinforced concrete structures and products. General technical requirements.
- GOST 13015.2-81* Prefabricated concrete and reinforced concrete structures and products. Marking.
- GOST 13015.3-81* Prefabricated concrete and reinforced concrete structures and products. Quality document.
- GOST 13015.4-84 Prefabricated concrete and reinforced concrete structures and products. Rules for transportation and storage.
- GOST 11024-84* External concrete and reinforced concrete wall panels for residential and public buildings. Specifications.
- GOST 12504-80* Internal concrete and reinforced concrete wall panels for residential and public buildings. General technical conditions.
- GOST 26434-85** Reinforced concrete floor slabs for residential buildings. Types and basic parameters.
- GOST 9561-91 Reinforced concrete hollow-core floor slabs for buildings and structures. Technical conditions.
- GOST 12767-94 Solid reinforced concrete floor slabs for large-panel buildings. General technical conditions.
- GOST 9574-90 Gypsum concrete panels for partitions. Technical conditions.
- GOST 25098-87 Reinforced concrete partition panels for buildings of industrial and agricultural enterprises. Technical conditions.
- GOST 17079-88 Reinforced concrete ventilation blocks. Technical conditions.
- GOST 17538-82* Reinforced concrete structures and products for elevator shafts of residential buildings. Technical conditions.
- GOST 18048-80* Reinforced concrete sanitary cabins. Technical conditions.
- GOST 9818-85* Reinforced concrete flights and landings of stairs. Technical conditions.
Geodetic work on the original horizon.
Geodetic work on the installation horizon.
Installation of external wall panels.
Installation of internal wall panels.
Installation of floor slabs.
Assemblies of external walls made of single-layer lightweight concrete panels according to series 2.130-1 issue 26.
Installation of ventilation units.
Instructions for the installation of volumetric blocks of elevator shafts from the series 1.189.1-11 Reinforced concrete structures for passenger elevator shafts of residential buildings with a floor height of 3.0 m (issue 1 and 2)
Installation of volumetric blocks of elevator shafts.
Installation of sanitary cabins.
Installation landings and marches.
Installation of partition panels.
Mounting units gypsum concrete partitions according to series 2.130-1 issue 27.
Mounting units for reinforced concrete partitions according to series 2.130-1 issue 27.
Sealing of joints and seams.
Sealing of joints of large-panel residential buildings.
Insulation of joints between window blocks and walls according to series 1.132.1-17.
Anti-corrosion protection of embedded and connecting products.
Installation of partitions from plasterboard sheets and panels.
Series 1.131.9-24 “Partitions made of plasterboard sheets for residential buildings”, issue 3 “Partitions element-by-element assembly on metal frame with sound insulation made of mineral wool slabs, mineral wool broaching mats with details for laying electrical communications.”
Nodes plasterboard partitions according to series 1.131.9-24 issue. 3

In PDF and HTML formats. 5.8 MB.

The price for this document is not yet known. Click the "Buy" button and place your order and we will send you the price.

Distributing regulatory documentation since 1999. We punch checks, pay taxes, accept all legal forms of payment without additional interest. Our clients are protected by law. LLC "CNTI Normocontrol"

Our prices are lower than other places because we work directly with document providers.

Delivery methods

  • Express courier delivery (1-3 days)
  • Courier delivery (7 days)
  • Pickup from the Moscow office
  • Russian Post

The manual is intended for customers (developers), construction and installation organizations, state construction supervision specialists, as well as engineering and technical workers directly involved in the construction of buildings and structures

  • Replaces Schemes for operational quality control of construction, repair, construction and installation works

Introduction

Regulatory documents regulating the quality of construction and installation works, building materials, products and structures

Methods of testing and quality control of building materials, products and structures during construction and installation work

Part 1. Construction work

A. Earthworks

1. Development of excavations (trenches) for structures

2. Development of pits using excavators

3. Development of trenches for pipelines in non-rocky soils

4. Postback

5. Vertical layout

6. Construction of embankments

B. Construction of foundations

7. Installation of strip foundation blocks

8. Installation of wall blocks in the underground part of buildings

9. Installation of glass-type foundation blocks

10. Device pile foundations

11. Arrangement of prefabricated grillages

12. Installation of monolithic grillages

13. Device horizontal waterproofing cement mortar foundations

IN. Concrete works

14. Installation of inventory formwork

15. Reinforcement work

16. Styling concrete mixtures

17. Construction of monolithic concrete and reinforced concrete walls

18. Construction of monolithic concrete and reinforced concrete columns

19. Construction of monolithic concrete and reinforced concrete foundations

G. Stone works

20. Wall masonry

21. Laying partitions

22. Laying pillars

D. Installation work

23. Installation of reinforced concrete columns of one-story buildings

24. Installation of precast concrete columns multi-storey buildings

25. Installation of reinforced concrete crossbars, beams, trusses

26. Installation of floor slabs and coverings

27. Installation flights of stairs and sites

28. Installation balcony slabs and jumpers

29. Installation of external wall panels of frame buildings

30. Installation of panels, blocks load-bearing walls buildings

31. Installation of volumetric blocks of elevator shafts

32. Installation of prefabricated reinforced concrete ventilation blocks

33. Installation of volumetric blocks

34. Installation of sanitary cabins

35. Installation of gypsum concrete partitions

36. Installation of asbestos-cement extrusion panels and slabs

37. Installation of frame-sheathing partitions

38. Installation of walls from sandwich panels and sheet assembly

39. Welding installation connections reinforced concrete structures

40. Anti-corrosion protection of steel embedded products

41. Sealing joints

42. Caulking joints and seams

43. Construction of a garbage chute

E. Roofing and insulation work

44. Preparation of foundations and underlying insulation and roofing elements

45. Thermal insulation device from bulk materials

46. ​​Installation of thermal insulation from slabs

47. Insulation device from roll materials

48. Insulation device made of polymer and emulsion-bitumen compositions

49. Roofing from rolled materials

50. Roofing from piece materials

51. Construction of a roof made of polymer and emulsion-bitumen compositions

52. Installation of a metal roof

G. Carpentry work

53. Installation of window blocks

54. Installation of door blocks

55. Construction of mezzanines, cabinets

H. Floor installation

56. Preparation of soil foundations for floors

57. Construction of a concrete underlying layer, screeds

58. Floor soundproofing device

59. Installation of glued floor waterproofing

60. Device bitumen waterproofing gender

61. Device monolithic coatings

62. Installation of floors from ceramic tiles

63. Installation of mosaic floors

64. Installation of floors from polymer materials

65. Laying joists in floors on floor slabs

66. Laying logs on posts on the ground base

67. Installation of plank floors

68. Installation of floors from piece parquet

69. Installation of floors from panel parquet

AND. Finishing work

70. Plastering works ( simple plaster)

71. Plastering works (improved plaster)

72. Plastering works (high-quality plaster)

73. Plastering works (coverings from sheets of dry gypsum plaster)

74. Painting works(painting with water-based compositions)

75. Painting work (painting with waterless compounds)

76. Cladding works

77. Wallpaper work

78. Glass work (glazing of bindings)

79. Glass work (installation of glass blocks and glass panels)

80. Installation of fiberglass fencing

81. Finishing (cladding) walls with panels, sheets with factory finishing

82. Montage suspended ceilings in building interiors

K. Improvement

83. Drainage device

84. Construction of a blind area made of concrete and asphalt concrete

85. Construction of sidewalks and paths from slabs

86. Construction of crushed stone base and asphalt concrete pavement

Part 2. Repair and construction work

1. Repair and strengthening of old foundations

2. Laying prefabricated reinforced concrete slabs floors during reconstruction brick buildings

3. Construction of monolithic sections in floors

4. Installation of floor slabs according to metal beams

5. Gain brick pillars and piers

6. Installation metal jumpers

7. Installation of stairs on metal stringers

8. Device rafter system from wooden elements

9. Plaster repair

10. Repair of plastering of building facades

11. Painting facades

12. Installation of molded parts of facades

13. Installation of drainpipes

Part 3. Installation work

1. Making holes and grooves for laying pipelines

2. Installation of cast iron pressure pipelines

3. Installation of pressure pipelines from asbestos-cement pipes

4. Installation of internal cold and hot water supply pipelines

5. Installation of reinforced concrete and concrete non-pressure pipelines

6. Installation sewer pipelines from ceramic pipes

7. System installation internal sewerage and drainage

8. Installation of water fittings

9. Installation of bathtub and washbasin

10. Installation of sanitary fixtures

11. Installation of an internal heating system

12. Installation of metal air ducts

13. Electric lighting device

14. Arrangement of round reinforced concrete wells

15. Installation of heating main cameras

16. Installation of non-passable channels

17. Insulation of heating pipelines

Introduction
Regulatory documents regulating the quality of construction and installation works, building materials, products and structures
Methods of testing and quality control of building materials, products and structures during construction and installation work
Part 1. Construction work
A. Earthworks
1. Development of excavations (trenches) for structures
2. Development of pits using excavators
3. Development of trenches for pipelines in non-rocky soils
4. Postback
5. Vertical layout
6. Construction of embankments
B. Construction of foundations
7. Installation of strip foundation blocks
8. Installation of wall blocks in the underground part of buildings
9. Installation of glass-type foundation blocks
10. Construction of pile foundations
11. Arrangement of prefabricated grillages
12. Installation of monolithic grillages
13. Installation of horizontal waterproofing of foundations made of cement mortars
B. Concrete work
14. Installation of inventory formwork
15. Reinforcement work
16. Laying concrete mixtures
17. Construction of monolithic concrete and reinforced concrete walls
18. Construction of monolithic concrete and reinforced concrete columns
19. Construction of monolithic concrete and reinforced concrete foundations
G. Stone works
20. Wall masonry
21. Laying partitions
22. Laying pillars
D. Installation work
23. Installation of reinforced concrete columns of one-story buildings
24. Installation of prefabricated reinforced concrete columns of multi-storey buildings
25. Installation of reinforced concrete crossbars, beams, trusses
26. Installation of floor slabs and coverings
27. Installation of staircases and landings
28. Installation of balcony slabs and lintels
29. Installation of external wall panels of frame buildings
30. Installation of panels, blocks of load-bearing walls of buildings
31. Installation of volumetric blocks of elevator shafts
32. Installation of prefabricated reinforced concrete ventilation blocks
33. Installation of volumetric blocks
34. Installation of sanitary cabins
35. Installation of gypsum concrete partitions
36. Installation of asbestos-cement extrusion panels and slabs
37. Installation of frame-sheathing partitions
38. Installation of walls from sandwich panels and sheet assembly
39. Welding of installation connections of reinforced concrete structures
40. Anti-corrosion protection of steel embedded products
41. Sealing joints
42. Caulking joints and seams
43. Construction of a garbage chute
E. Roofing and insulation work
44. Preparation of foundations and underlying insulation and roofing elements
45. Thermal insulation device from bulk materials
46. ​​Installation of thermal insulation from slabs
47. Insulation device made from rolled materials
48. Insulation device made of polymer and emulsion-bitumen compositions
49. Roofing from rolled materials
50. Roofing from piece materials
51. Construction of a roof made of polymer and emulsion-bitumen compositions
52. Installation of a metal roof
G. Carpentry work
53. Installation of window blocks
54. Installation of door blocks
55. Construction of mezzanines, cabinets
H. Floor installation
56. Preparation of soil foundations for floors
57. Construction of a concrete underlying layer, screeds
58. Floor soundproofing device
59. Installation of glued floor waterproofing
60. Installation of bitumen floor waterproofing
61. Installation of monolithic coatings
62. Installation of ceramic tile floors
63. Installation of mosaic floors
64. Construction of floors made of polymer materials
65. Laying joists in floors on floor slabs
66. Laying logs on posts on the ground base
67. Installation of plank floors
68. Installation of block parquet floors
69. Installation of floors from panel parquet
I. Finishing work
70. Plastering works (simple plaster)
71. Plastering works (improved plaster)
72. Plastering works (high-quality plaster)
73. Plastering works (coatings made of sheets of dry gypsum plaster)
74. Painting work (painting with water-based compositions)
75. Painting work (painting with waterless compounds)
76. Facing work
77. Wallpaper work
78. Glass work (glazing of bindings)
79. Glass work (installation of glass blocks and glass panels)
80. Installation of fiberglass fencing
81. Finishing (cladding) walls with panels, sheets with factory finishing
82. Installation of suspended ceilings in building interiors
K. Improvement
83. Drainage device
84. Construction of a blind area made of concrete and asphalt concrete
85. Construction of sidewalks and paths from slabs
86. Construction of crushed stone base and asphalt concrete pavement
Part 2. Repair and construction work
1. Repair and strengthening of old foundations
2. Laying prefabricated reinforced concrete floor slabs during the reconstruction of brick buildings
3. Construction of monolithic sections in floors
4. Installation of floor slabs on metal beams
5. Strengthening brick pillars and piers
6. Installation of metal jumpers
7. Installation of stairs on metal stringers
8. Construction of a rafter system made of wooden elements
9. Plaster repair
10. Repair of plastering of building facades
11. Painting facades
12. Installation of molded parts of facades
13. Installation of drainpipes
Part 3. Installation work
1. Making holes and grooves for laying pipelines
2. Installation of cast iron pressure pipelines
3. Installation of pressure pipelines from asbestos-cement pipes
4. Installation of internal cold and hot water supply pipelines
5. Installation of reinforced concrete and concrete non-pressure pipelines
6. Installation of sewer pipelines from ceramic pipes
7. Installation of an internal sewerage and drainage system
8. Installation of water fittings
9. Installation of bathtub and washbasin
10. Installation of sanitary fixtures
11. Installation of an internal heating system
12. Installation of metal air ducts
13. Electric lighting device
14. Construction of round reinforced concrete wells
15. Installation of heating main cameras
16. Installation of non-passable channels
17. Insulation of heating pipelines


SCHEMES OF INPUT AND OPERATIONAL QUALITY CONTROL OF CONSTRUCTION AND INSTALLATION WORKS

Part IV, Issue 2

HEATING NETWORK

GEODETIC WORK

GEODETIC WORK WHEN LAYING PIPELINES

TECHNICAL REQUIREMENTS

SNiP 12-01-2004 Organization of construction.

SNiP 11-02-96. Engineering surveys for construction. Basic provisions.

SP 11-104-97 Engineering and geodetic surveys for construction.

GOST R 51872-2002 Geodetic executive documentation. Execution rules.

SNiP 3.01.03-84 Geodetic work in construction.

A manual for geodetic work in construction (to SNiP 3.01.03-84).

Geodetic work when laying pipelines is mandatory integral part technologies for the production of pipeline laying works (self-control, operational control and acceptance control).

Geodetic control means, along with mechanical ones, provide the ability to lay pipelines in the design position (self-control), provide the ability to monitor the compliance of the position of pipelines and its elements with design and regulatory requirements both during installation (operational control) and upon its completion (acceptance control through executive geodetic survey of the planned and altitude position of the laid pipeline).

Before starting work on laying the pipeline, it is necessary to check:


Availability of PPGR, technological map and SOKK or as part of the PPR technological documentation for carrying out geodetic work when laying pipelines, containing methods for performing detailed alignment work, a diagram of the location of signs, marks and landmarks, the order and volume of work performed;

Availability of a road layout certificate; the presence of an as-built drawing based on the results of staking out and fixing the places of connections and connections of communications, angles of rotation of the pipeline, wells, chambers, channels, tunnels, intersections of the pipeline with other networks;

Safety of signs of the external alignment network of the pipeline and axial signs, immutability of their position through repeated measurements of network elements; restoration of lost signs;

Availability of certificates of inspection of previously completed earthworks for the construction of trenches and pits, certificates of acceptance of trenches and pits;

Availability of an as-built drawing (scheme) based on the results of a geodetic check of the compliance of the planned and altitude positions of trenches and pits with the design ones; the presence in the drawing of confirmation by the customer of the correctness of the preparation and compliance of the as-built drawing with nature;

Conducting training for workers in labor organization and methods for aligning pipes and other pipeline elements horizontally and vertically.

Controlled Operations

Composition and controls

Documentation

Preparatory work

Check:

Availability of PPGR, technological map and SOKK, or as part of the PPR technological documentation for carrying out detailed alignment work when laying pipelines utility networks;

PPR, PPGR, routing and SOKK

Availability of an as-built drawing based on the results of staking out the pipeline route;

As-built drawing

Preservation and invariability of the position of the pipeline network alignment signs, axial signs and signs that establish in nature the axis of the route, the beginning and end of the route, wells; restoration of lost signs;

General work log

Availability of inspection certificates for previously completed earthworks and acceptance certificates for trenches and pits;

Certificates of inspection of hidden work

Availability of an as-built drawing based on the results of a geodetic as-built survey of completed trenches and pits with the customer’s permission to lay the pipeline.

As-built drawing

Geodetic work when laying pipelines

Control:

Compliance with the specified technology for geodetic work when laying pipelines;

Accuracy of marking work;

Geodetic control log

Laying pipes, wells, chambers, channels, tunnels in the design position (deviations in plan and height from the marks provided by the PPR using permanent and running sights, beacons, benchmarks, moorings, level, theodolite, laser devices).

Executive geodetic schemes

Check:

Compliance of the actual position of the pipeline and other structures with the requirements of the project and regulatory documents based on the results of instrumental geodetic survey;

As-built drawing

Proper execution of the as-built drawing based on the results of the as-built survey and receipt of confirmation by the customer of the correctness of the as-built drawing in situ.

INPUT AND OPERATIONAL CONTROL is carried out by:

foreman (foreman), surveyor - in the process of work

ACCEPTANCE CONTROL IS CARRIED OUT BY:

foreman (master), representatives of technical supervision of the customer and operating organizations

Instrumentation - level, theodolite, sights, wire, moorings, cast-offs, slats, measuring tape, laser devices and etc.

Geodetic work when laying pipelines is an integral part technological process production of work. They must be carried out in accordance with the requirements of SNiP 3.01.03-84, PPR, PPGR, operational quality control schemes and other technological documentation of the quality management system operating in the enterprise.

Before starting work on laying pipelines, the position of the pipeline axis must be secured.

The axis of the route is projected into the trench with a theodolite or a plumb line from a tensioned wire between the pivot points of the axis or turning points.

Fixing the position of the axis of the route, especially wells, can be done using castings, arranged on straight sections of the route at a distance of 40-50 m from one another, as well as at turning points. For cast-offs ( edged boards, attached horizontally to the pillars above the trench, or inventory engineering cast-offs) take out and fix the axes between which the string is stretched. From the string, the axis is transferred by plumb lines to the bottom of the trench.

Laying out the design slope of the trench bottom after completing shortfalls and making up for overshoots and breaking out the bottom of pits for sealing pipeline joints can be done using permanent (fixed) and running sights, geometric leveling, optical levels and laser slope clamps. Marks of permanent (fixed) sights attached to inventory cast-offs, or nailed to a wooden cast-off, or installed on the edge of a trench, are made by a level taking into account the design slope of the trench..jpg" height="17"> - design slope of the trench, DIV_ADBLOCK866">


Laying out the height of the bottom of trenches, pits and pits and relocating the pipeline axis using fixed and moving sights

https://pandia.ru/text/80/203/images/image005_11.gif" width="418" height="198 src=">

1. Fixed cast-offs 2. Running sights 3. Fixed sights on the edge of the trench

When monitoring using the method of geometric leveling along the axis, every 15-20 m, stakes are driven in, placed at a convenient distance from the axis, they are leveled and on each mark the depth of the trench is written, calculated from the difference between the design mark and the mark of the peg. The depth of the trench is controlled by a rod with centimeter divisions, along which the clamp and slider are mixed. The clamp is fixed at a mark equal to the depth of the trench from the top cut of the peg.

Automatic regulation of the trench depth can be performed using various slope sensors installed on the earthmoving machine (pendulum, electronic level, gyroscope) or using slope sensors installed parallel to the axis of the route separately from the earthmoving machine (string, laser light beam).

Laying out a well pit includes securing the center of the well, installing a cast-off fixed at a distance of 0.6-0.7 m from the edge of the trench, and transferring marks and axes to the cast-off.

Laying pipes in height can be carried out:

When building on a prepared foundation (by beacons) according to the level;